Expansion of National Roads 1, 3, 4 and 6 (P11-L3)
The project implemented by the General Department of Public Works (GDPW) entails widening of all or part of NR/NH 1, NR/NH 3, NR/NH 4, and NR/NH 6.
Currently, the project is ongoing and has been achieved 96,13% of overall progress. In fact, the main activities under this project are as follows:
- Widening of NR/NH 1 has been completed (100%)
- Widening of NR/NH 3 has been progress 89%
- Widening of NR/NH 4 which has not been started yet
- Widening of NR/NH 6 has been progress 90.4%
This project also encounters some challenges including:
- Compensation/resettlement on the NR/NH 3 (4 lanes) for urban area has been
slow. - The maintenance/repair of road damage on the old road is not on time which
affected the traffic. - Dust that affects traffic and people on both sides of the road
- Insufficient number of construction site sign
- There are protests from some resident that do not want to build a road park/garden on the middle lane, which has hindered the construction of the road
for a while - There is a delay in the construction of the first bridge because the market-owner
and some resident want to delay and relocate the project site - The floods in October 2020, have impact some sections of the road and damage
the existing road foundations and some bridge works - The COVID-19 pandemic also affects both domestic and foreign workers.